Estimates and velocity

Enable task sizes in the board settings and each task can have a size (S / M / L / XL). The default points are S=1, M=5, L=15, XL=45, and you can change them in the board settings.

On a board without sizes enabled, each task counts as 1 point. On a board with sizes enabled, you can also choose whether cards without a size count as 1 point.

Velocity is the total size of work completed in a period. View it under Insights → Analytics → Velocity.

Use velocity to set realistic due dates.

Divide the remaining total size by velocity to estimate the time needed. This gives a date based on the pace you have actually sustained.

For the steps, see Set realistic due dates from velocity.

  • Size tasks consistently. If unsized tasks are excluded, velocity will undercount the work completed.
  • Agree on a shared sizing scale. The absolute numbers matter less than stable relative sizes.
  • Mark completed work as complete. Otherwise it will not appear in the totals.
  • Collect several weeks of data. One or two weeks can vary too much to support a reliable plan.