Set realistic due dates from velocity
Use this when: You are asked for dates without having a basis for them, or work repeatedly finishes late.
Before you start
Section titled “Before you start”You need:
- Sizes on tasks; see Estimates and velocity
- Completed work consistently marked complete
- Several weeks of data; one or two weeks can vary too much
1. Check velocity
Section titled “1. Check velocity”Open Insights → Velocity and review completed size over recent weeks.
Use a lower recent value as a conservative starting point. An average can leave too little room for slower weeks.
2. Count the remaining size
Section titled “2. Count the remaining size”Filter to the relevant project and total the sizes of incomplete tasks.
3. Divide
Section titled “3. Divide”Estimated weeks ≈ Remaining total size / Weekly velocityThis estimates the time needed at the pace you have sustained.
4. Adjust for the actual schedule
Section titled “4. Adjust for the actual schedule”Account for differences between the historical pace and the planned work:
- Shared availability: Divide by the fraction of capacity available to this project, if your baseline assumes full availability.
- Holidays and leave: Exclude those days from the working calendar.
- Waiting for review: Check actual waiting time in Risks and allow for it where it is not already reflected in the baseline.
Avoid counting the same constraint twice. Long review waits can dominate the schedule: reducing coordination delays may matter more than speeding up execution.
5. Show the reasoning
Section titled “5. Show the reasoning”For example: “We have 80 points remaining. At 18 points per week and 70% availability, that is about 6.3 weeks. Adding two days for review gives us roughly seven weeks.”
This makes the assumptions open to discussion, instead of relying on “probably by the end of the month.”
If work finishes late
Section titled “If work finishes late”Find out where the extra time went:
- Slower execution shows up in velocity.
- Longer waits show up in Risks.
If waiting is the cause, adding more people to execution may not help. See Reduce time waiting for review.